What you getEST

An estimate you can check line by line.

Quantities with units, the assumptions behind them, what stays out, and the questions to settle before the number is used.

Electrical takeoffE-101LED troffers24 EALED downlights10 EADuplex receptacles42 EASwitches and sensors14 EABranch conduit and wire1,850 LFPanelboard LP-11 EAConfirm homerun lengths
A takeoff sheet: quantities and units by scope item, one line marked as an open question.

The takeoff

Quantities by trade, from one plan.

Choose a trade to see its takeoff for a single-story office of 1,960 SF (56' x 35'). Each line names the item, how it was counted, the quantity and the unit.

Choose a trade to show its takeoff
Painting takeoff: scope items with quantities and units.
Scope itemQuantityUnit
Wall preparationPatch, sand, spot-prime gypsum walls3,636SF
Walls, two finish coatsEggshell latex over prepared gypsum3,636SF
Gypsum ceilingsCorridor and break room, flat latex, two coats417SF
Doors and framesSemi-gloss enamel, both faces8EA
Accent wallConference room east wall, specified color126SF

Open questions we raise

  • Finish schedule sheen conflicts with the painting specification
  • Door frames shown as factory-finished on one sheet and field-painted on another
  • Exposed ceilings, deck and ductwork: painted or left as is

Typically excluded

  • Surface repairs beyond the specified preparation
  • Hazardous material testing or abatement
  • Site visits and field verification of existing conditions
Painting estimating details
Drywall takeoff: scope items with quantities and units.
Scope itemQuantityUnit
Partition type A3-5/8" studs at 16" o.c., 5/8" board each side, to deck85LF
Partition type B, sound ratedType A plus acoustic batts, conference and restroom53LF
Exterior wall furringHat channel with 5/8" board, interior face182LF
Gypsum board ceilingsSuspended framing, 5/8" board, Level 4 finish417SF
Framed openingsDoor and window headers and jambs20EA

Open questions we raise

  • Partition heights: to the deck or a set distance above the ceiling
  • Wall tag on the plan does not match the wall type legend
  • Fire rating on the life safety plan missing from the wall type

Typically excluded

  • Framing design, stud engineering or deflection calculations
  • Code review of rated assemblies
  • Site visits and field measurement of existing walls
Drywall estimating details
Flooring takeoff: scope items with quantities and units.
Scope itemQuantityUnit
Carpet tile CPT-1Open office, conference and offices1,348SF
Luxury vinyl tile LVT-1Break room and corridor417SF
Porcelain tile PT-1Restroom, thinset on prepared slab195SF
Rubber base RB-14" coved, at all floor finishes452LF
Transition stripsAt changes in floor finish6EA

Open questions we raise

  • Finish tag on the plan has no matching product in the specification
  • Transition between carpet and resilient flooring not detailed
  • Concrete moisture testing and mitigation not assigned to a trade

Typically excluded

  • Moisture testing and mitigation unless added to the scope
  • Moving furniture or equipment
  • Site visits and field verification of existing floors
Flooring estimating details
Ceilings takeoff: scope items with quantities and units.
Scope itemQuantityUnit
Acoustical panel ceiling ACT-12x2 lay-in panels, 15/16" grid1,348SF
Moisture-resistant panels ACT-2Restroom, 2x2 lay-in195SF
Perimeter wall angleAt all acoustical ceiling walls376LF
Hanger wires and bracingPer grid layout, to structure1,543SF

Open questions we raise

  • Ceiling height on the reflected ceiling plan differs from the building section
  • Seismic bracing requirements for the grid not stated
  • Panel type in the legend not found in the specification

Typically excluded

  • Seismic bracing design or engineering
  • Gypsum board ceilings and soffits unless added to the scope
  • Site visits and field verification of existing ceilings
Ceilings estimating details
Doors takeoff: scope items with quantities and units.
Scope itemQuantityUnit
Hollow metal frames16 ga welded, 3'-0" x 7'-0"8EA
Flush wood doorsInterior, 1-3/4", factory finished6EA
Hollow metal doorsInsulated, exterior2EA
Hardware sets HW-1 to HW-3Locksets, hinges, closers, exit devices8EA

Open questions we raise

  • Opening on the floor plan missing from the door schedule
  • Fire rating on the life safety plan differs from the door schedule
  • Hardware set named on the schedule is not defined in the specification

Typically excluded

  • Writing hardware specifications or preparing submittals
  • Access control wiring and programming
  • Code review of egress and fire ratings
Doors estimating details
Electrical takeoff: scope items with quantities and units.
Scope itemQuantityUnit
2x2 LED troffersLay-in, 0-10 V dimming24EA
LED downlightsCorridor and break room10EA
Duplex receptacles20 A, at walls per plan42EA
Switches and occupancy sensorsPer room14EA
Branch conduit and wireEMT with THHN, home runs to LP-11,850LF
Panelboard LP-1225 A, 42 circuit1EA

Open questions we raise

  • Fixture type on the plan missing from the fixture schedule
  • Circuiting and homeruns not shown, so branch routing is assumed
  • Equipment connection responsibility not assigned between trades

Typically excluded

  • Electrical design, load calculations or code review
  • Utility company charges and service work by others
  • Fire alarm, security and low-voltage systems unless added to the scope
Electrical estimating details
Plumbing takeoff: scope items with quantities and units.
Scope itemQuantityUnit
Water closetWall-hung, with carrier1EA
LavatoryWall-hung, with faucet1EA
Break room sinkStainless, single bowl1EA
Water heaterElectric, point of use1EA
Domestic water pipingCopper, 1/2" to 1", hot and cold, insulated120LF
Sanitary waste and ventPVC, 2" to 4", with vents through roof90LF

Open questions we raise

  • Pipe size missing on part of a branch or riser
  • Fixture tag on the plan has no match in the fixture schedule
  • Point of connection to site utilities not located

Typically excluded

  • Plumbing design, sizing calculations or code review
  • Site utilities beyond the point of connection unless added to the scope
  • Permit and utility connection fees
Plumbing estimating details
HVAC takeoff: scope items with quantities and units.
Scope itemQuantityUnit
Supply ductworkGalvanized trunk and branches130LF
Supply diffusers24x24 lay-in18EA
Return grilles24x24 lay-in8EA
VAV terminal unitsWith controls3EA
Restroom exhaust fanCeiling mounted, ducted1EA

Open questions we raise

  • Duct sizes missing on branch runs
  • Air device on the plan has no matching schedule tag
  • Controls and control wiring split between mechanical and electrical not stated

Typically excluded

  • Mechanical design, load calculations or code review
  • Testing, adjusting and balancing unless added to the scope
  • Temperature controls unless added to the scope
HVAC estimating details
Concrete takeoff: scope items with quantities and units.
Scope itemQuantityUnit
Slab on grade5" with vapor retarder1,960SF
Continuous footings24" x 12", perimeter13.5CY
Reinforcing steel#4 at 18" each way, #5 in footings2,355LB
Edge formsFooting and slab edges440SF

Open questions we raise

  • Footing schedule dimensions differ from the foundation plan
  • Slab thickness or reinforcing at depressions not detailed
  • Lap lengths not listed in the structural notes

Typically excluded

  • Structural design, mix design or engineering
  • Testing and inspection services
  • Dewatering and unsuitable soil removal unless added to the scope
Concrete estimating details
Masonry takeoff: scope items with quantities and units.
Scope itemQuantityUnit
8" CMU exterior wallsStandard units, running bond, 12' high1,950SF
Bond beamsTwo courses, grouted and reinforced364LF
Cell groutVertical cells at 32" o.c.9CY
Vertical reinforcing#5 bars at 32" o.c. and at jambs70EA

Open questions we raise

  • Grouted cell spacing differs between the structural notes and wall sections
  • Lintel type not scheduled at some openings
  • Veneer anchor or flashing details missing at a wall type

Typically excluded

  • Structural design or engineering of masonry walls
  • Special inspection and testing
  • Cold weather protection unless added to the scope
Masonry estimating details
Roofing takeoff: scope items with quantities and units.
Scope itemQuantityUnit
TPO membrane60 mil, mechanically attached19.6SQ
Tapered roof insulationPolyiso, sloped to drains1,960SF
Perimeter edge metalPrefinished, with cleats182LF
Roof drains and overflowsWith sumps2EA
Curbs and penetrationsRooftop unit curb and vents5EA

Open questions we raise

  • Tapered insulation layout not provided, so slope and thickness are assumed
  • Edge metal profile differs between the roof plan and the details
  • Manufacturer warranty type and term not stated

Typically excluded

  • Roof design, wind uplift or drainage calculations
  • Tear-off of existing roofing unless added to the scope
  • Deck repairs, site visits and field verification
Roofing estimating details
Sitework takeoff: scope items with quantities and units.
Scope itemQuantityUnit
ExcavationBuilding pad and parking180CY
Structural fillPlaced and compacted120CY
Asphalt paving2" surface on 6" base1,067SY
Concrete curb and gutterStandard section320LF
Concrete sidewalks4" with control joints640SF
Storm structuresInlets with connections2EA

Open questions we raise

  • Topsoil stripping depth not stated in the plans or geotechnical report
  • Shrink and swell factors to apply to cut and fill
  • Allowance for unsuitable soil or rock not defined

Typically excluded

  • Surveying, staking and field verification
  • Geotechnical investigation or testing
  • Dewatering, rock removal and unsuitable soils unless added to the scope
Sitework estimating details

How to read it

Five things a useful estimate shows.

  1. Plan basis

    Every quantity ties to a sheet and a revision, so a changed plan shows which lines move.

  2. Quantity, unit, basis

    Each line keeps the measured quantity, its unit and how it was counted apart, so each can be checked on its own.

  3. Your rates

    Rates and pricing assumptions come from you. We do not invent them.

  4. What it depends on

    Assumptions and exclusions sit next to the number, not buried under it.

  5. Open questions

    Conflicts and gaps are listed for you to resolve before the estimate is used.