The basis of estimate is the document that explains how the number was built. Here is what goes in it, a filled example and a template to start from.

Free. No sign-up and no email address.

Rather not fill it in? Send the plans and we return the takeoff and estimate. Fixed quote within 2 business hours.

Get a fixed quote

Short answer

A basis of estimate (BOE) is the document that explains a cost estimate: its purpose, the scope it covers, where the quantities and prices came from, the allowances, assumptions and exclusions, and the risks. AACE International describes it as the one deliverable that defines the scope of the project and later becomes the basis for change management.

What is a basis of estimate?

AACE International’s Recommended Practice 34R-05 says a well-written BOE states the purpose of the estimate, the project scope, pricing basis, allowances, assumptions, exclusions, cost risks and opportunities, and any deviations from standard practices. It travels with the estimate so that someone who did not build the number can follow it.

What goes in a basis of estimate

SectionWhat it says
Purpose and classWhy the estimate was prepared and how detailed it is
ScopeWhat is included, by division or trade
DocumentsDrawings, specifications and addenda priced, with dates
QuantitiesHow they were measured and by whom
Pricing basisWhere labor, material, equipment and subcontract prices came from
AllowancesAmounts carried for items not yet defined
AssumptionsConditions the price depends on
ExclusionsWhat is not in the number
Contingency and escalationHow risk and price changes over time are covered
Risks and opportunitiesWhat could move the number either way

Short on time? Send the plans and specs and we do this for you. Fixed quote within 2 business hours. Plan review is free, and you pay only after you accept.

Get a fixed quote

Basis of estimate example: a tenant fit-out drywall estimate

  • Purpose: bid estimate for the drywall and framing subcontract.
  • Scope: metal stud partitions, gypsum board, finishing to the levels in section 09 29 00, acoustical insulation in rated walls.
  • Documents: architectural sheets and specification sections listed by number and date, addenda 1 and 2.
  • Quantities: measured by wall type from the floor plans and partition schedule; heights from the sections.
  • Pricing basis: material from current supplier quotes; labor at the company’s production rates and wages.
  • Allowances: none.
  • Assumptions: normal working hours; owner provides a clear floor.
  • Exclusions: firestopping, ceilings, painting.
  • Risks: partition heights not shown in two areas; listed as open questions.

Free basis of estimate template (Word)

The download above is a Word template with each section as a heading and a prompt under it. Fill it in as you build the estimate, not after. It carries the Bidmere name and site address in the footer; delete them if you like.

Basis of estimate on federal and public work

Agencies and owners that ask for cost proposals often want each cost element explained, which is what a BOE does. Follow the solicitation’s own instructions first. See federal negotiated proposals and the sample estimate for how assumptions and exclusions are written.

Frequently asked questions

What is a basis of estimate?

The document that explains a cost estimate: purpose, scope, documents priced, how quantities and prices were set, allowances, assumptions, exclusions, contingency and risks.

Who prepares the basis of estimate?

The estimator who builds the number, at the same time as the estimate.

Is there a basis of estimate template?

Yes. The free Bidmere template is a Word file with one heading and prompt per section.

What is the difference between assumptions and exclusions?

An assumption is a condition the price depends on; an exclusion is work that is not in the price at all.

Get a fixed quote

Share the project basics. You get a fixed price and delivery date within 2 business hours. Plan review is free, and you pay only after you accept.

A sentence or two is enough. Leave private rates out of this box.
Add details (optional)
Share a view-only link if you have one. It lets us quote faster; you can also send documents after we reply.

Preparing the form…

* Required. We reply by email within 2 business hours. Plan review and quotes are free.

Sources