Bid process · 5 min read

How to handle addenda on a construction bid

Addenda are formal changes to a solicitation issued before bids are due. They can change scope, quantities, specifications, forms or the due date. Track every addendum, update your pricing and subcontractor quotes, and acknowledge each one exactly as the solicitation requires; on public bids, failing to acknowledge a material addendum can make a bid nonresponsive.

What an addendum is

An addendum, called an amendment in federal invitations for bids, modifies the solicitation documents before the bid opening. Owners issue them to answer questions, correct errors, revise specifications or quantities, or change the schedule. Once issued, an addendum is part of the bid documents.

Track every addendum

Late addenda are common, sometimes days or hours before bids are due. Keep a single log that every estimator and the person submitting the bid can see.

  • Number and date of each addendum, and where it was posted.
  • Sections, sheets, bid items or forms affected.
  • Whether pricing, subcontractor scope or schedule must change.
  • Who checked it, and when subcontractors and suppliers were notified.

Acknowledge it the required way

Solicitations specify how addenda must be acknowledged: on the bid form, on a separate form, by signing the addendum or through the bidding portal. In federal sealed bidding, FAR 52.214-3 requires bidders to acknowledge amendments. FAR 14.405 allows a contracting officer to waive failure to acknowledge an amendment only in limited cases, such as when the amendment has no or trivial effect on price, quality, quantity or delivery.

Update prices and quotes

Ask subcontractors and suppliers to confirm that their quotes include each addendum. A quote that does not reference the latest addendum may exclude new work.

How Bidmere helps

Bidmere includes addenda in the requirement tracker for each bid package and flags acknowledgments that still need to be completed. Your team keeps responsibility for pricing and submission.

Common questions

What happens if I miss an addendum?

On public sealed bids, failing to acknowledge a material addendum can make the bid nonresponsive. Owners may waive it only in limited cases.

Can an addendum change the bid due date?

Yes. Owners often use addenda to extend the due date or change the bid opening location or method.

Should subcontractor quotes reference addenda?

Yes. Ask each subcontractor and supplier to state which addenda their quote includes.

Sources